Capital programme 2024/25: first quarter monitoring
The committee supported the recommendations, subject to a review of the schemes carried forward from 2023/24. It recommended to Cabinet that the net addition of £4.085m be approved, that the total programme of £101.643m be noted, and that carried-forward schemes be reviewed next quarter, with a focus on those that will incur borrowing.
Cabinet. The Cabinet makes most of the council's decisions.
Capital programme 2024/25: first quarter review
The Cabinet approved a net addition of £4.085m to the total capital programme. It noted the total programme of £101.643m. It asked for the schemes carried forward from 2023/24 to be reviewed next quarter, with a focus on those that will need borrowing.
Finance and Resources Overview and Scrutiny Committee. Scrutiny committees question decisions and can recommend changes. They don't make the decision.
Revised capital programme 2025/26, quarter one
The committee recommended that Cabinet approve a net addition of £18.180m to the capital programme. It also recommended that Cabinet note the total programme of £106.207m and the first-quarter capital outturn.
Cabinet. The Cabinet makes most of the council's decisions.
Capital programme monitoring, first quarter 2025/26
The Cabinet approved a net addition of £18.180m to the capital programme. It also approved the total programme of £106.207m and the first-quarter spending position.
Items are linked when their titles share most of their words and they fall within 18 months of each other. Councils don't number reports across meetings, so a few links may be wrong, and a step may be missing if its title changed a lot. Each step links to the meeting, where the council's own papers are.