Finance and Resources Overview and Scrutiny Committee. Scrutiny committees question decisions and can recommend changes. They don't make the decision.
Capital programme 2024/25, quarter two monitoring
The committee recommended to Cabinet that a net addition of £0.551m to the capital programme be approved. It also recommended that the total programme of £102.194m and the quarter two position be noted.
Cabinet. The Cabinet makes most of the council's decisions.
Capital programme: second-quarter monitoring
Cabinet noted a net addition of £0.551m to the total Capital Programme. It also noted the total programme of £102.194m and the second-quarter capital spending position for 2024/25.
Finance and Resources Overview and Scrutiny Committee. Scrutiny committees question decisions and can recommend changes. They don't make the decision.
Revised capital programme 2025/26: quarter two monitoring
The committee recommended to Cabinet that the net addition of £6.956m to the total capital programme be approved. It noted the total capital programme of £113.163m and the second quarter spending position for 2025/26.
Cabinet. The Cabinet makes most of the council's decisions.
Capital programme: net addition of £6.956m approved
Cabinet approved a net addition of £6.956m to the total capital programme. It noted that the total programme is £113.163m and the second-quarter spending position for 2025/26.
Items are linked when their titles share most of their words and they fall within 18 months of each other. Councils don't number reports across meetings, so a few links may be wrong, and a step may be missing if its title changed a lot. Each step links to the meeting, where the council's own papers are.